Petroleum Exploration (Pvt.) Ltd

Kandra Gas Field & Power Development

Kandra Power Company (KPC), a sister concern of PEL is going to set up a 120MW power plant utilizing the gas produced by the Kandra Gas Field from12-14 wells. This gas field development and power project costs are estimated to be USD110 million and USD 180 million respectively. The field has Initial Gas In Place of 3.36 TCF.

The processed Kandra gas (40 MMSCFD) of 300 BTU will be commingled with 10 MMSCFD pipeline quality gas of 900-950 BTU/SCF heating value which will result in 50 MMSCFD of 430 BTU quality gas.

  • Province:                                 Sindh
  • Area:                                         314.43 km2
  • Geological Setting:                 Khairpur-Jacobabad High
  • Play Type:                                 Structural
  • Resource Potential:                 ~ 2 TCF

Key Features

The block holds good potential for structural traps in Chiltan, Loralai, Alozai (Jurassic) and Wulgai (Triassic) formations.

Petroleum system well established in the area (Wulgai TOC=1.3-1.4%& Alozai TOC=1.1%)

Kandra-4 Deep tested 800+ BTU in Chiltan Limestone.

Well-developed gas infrastructure in the area.

The processed Kandra gas (40 MMSCFD) of 300 BTU will be commingled with 10 MMSCFD pipeline quality gas of 900-950 BTU/SCF heating value which will result in 50 MMSCFD of 430 BTU quality gas.

Introduction

  • Province:                               Sindh
  • Area:                                       314.43 km2
  • Geological Setting:               Khairpur-Jacobabad High
  • Play Type:                               Structural
  • Resource Potential:              ~ 2.86TCF

Key Features

The block holds good potential for the development of a gas field at the level of Sui Main Limestone

Petroleum system is established in the area

Well-developed gas infrastructure within the block.

FIELD DEVELOPMENT

The field development envisages drilling and completing 12-14 additional wells, surface gathering lines and central processing facility for producing 120 MMSCFD of raw gas.
The low heating value Kandra gas (150 BTU/SCF) @ 40 MMSCFD after processing to 300 BTU will be used as fuel of 430 BTU for power generation after processing and comminling with 10 MMCFD pipeline quality gas.

POWER PROJECT

The processed Kandra gas (40 MMSCFD) of 300 BTU will be commingled with 10 MMSCFD pipeline quality gas of 900-950 BTU/SCF heating value which will result in 50 MMSCFD of 430 BTU quality gas.

This gas will be used as fuel for Combined Cycle Power Project of 120 megawatts electricity to be set up by Kandra Power Company.

Petroleum Exploration (Pvt.) Ltd

Kandra gas field & power development

Petroleum Exploration (Pvt.) Ltd

Kandra Power Company (KPC), a sister concern of PEL is going to set up a 120MW power plant utilizing the gas produced by the Kandra Gas Field from 12-14 wells. This gas field development and power project costs are estimated to be USD110 million and USD 180 million respectively. The field has Initial Gas In Place of 3.36 TCF.

The processed Kandra gas (40 MMSCFD) of 300 BTU will be commingled with 10 MMSCFD pipeline quality gas of 900-950 BTU/SCF heating value which will result in 50 MMSCFD of 430 BTU quality gas.

Introduction

  • Province:
  • Area:
  • Geological Setting:
  • Play Type:
  • Resource Potential:
  • Sindh
  • 314.43 km2
  • Khairpur-Jacobabad High
  • Structural
  • ~ 2 TCF

Key Features

The block holds good potential for structural traps in Chiltan, Loralai, Alozai (Jurassic) and Wulgai (Triassic) formations.

Petroleum system well established in the area (Wulgai TOC=1.3-1.4%& Alozai TOC=1.1%)

Kandra-4 Deep tested 800+ BTU in Chiltan Limestone.

Well-developed gas infrastructure in the area.

The processed Kandra gas (40 MMSCFD) of 300 BTU will be commingled with 10 MMSCFD pipeline quality gas of 900-950 BTU/SCF heating value which will result in 50 MMSCFD of 430 BTU quality gas.

Introduction

  • Province:
  • Area:
  • Geological Setting:
  • Play Type:
  • Resource Potential:
  • Sindh
  • 314.43 km2
  • Khairpur-Jacobabad High
  • Structural
  • ~ 2.86TCF

Key Features

The block holds good potential for the development of a gas field at the level of Sui Main Limestone

Petroleum system is established in the area

Well-developed gas infrastructure within the block.

FIELD DEVELOPMENT

The field development envisages drilling and completing 12-14 additional wells, surface gathering lines and central processing facility for producing 120 MMSCFD of raw gas.
The low heating value Kandra gas (150 BTU/SCF) @ 40 MMSCFD after processing to 300 BTU will be used as fuel of 430 BTU for power generation after processing and comminling with 10 MMCFD pipeline quality gas.

POWER PROJECT

The processed Kandra gas (40 MMSCFD) of 300 BTU will be commingled with 10 MMSCFD pipeline quality gas of 900-950 BTU/SCF heating value which will result in 50 MMSCFD of 430 BTU quality gas.

This gas will be used as fuel for Combined Cycle Power Project of 120 megawatts electricity to be set up by Kandra Power Company.

The processed Kandra gas (40 MMSCFD) of 300 BTU will be commingled with 10 MMSCFD pipeline quality gas of 900-950 BTU/SCF heating value which will result in 50 MMSCFD of 430 BTU quality gas.

Introduction

  • Province:
  • Area:
  • Geological Setting:
  • Play Type:
  • Resource Potential:
  • Sindh
  • 314.43 km2
  • Khairpur-Jacobabad High
  • Structural
  • ~ 2 TCF

Key Features

The block holds good potential for structural traps in Chiltan, Loralai, Alozai (Jurassic) and Wulgai (Triassic) formations.

Petroleum system well established in the area (Wulgai TOC=1.3-1.4%& Alozai TOC=1.1%)

Kandra-4 Deep tested 800+ BTU in Chiltan Limestone.

Well-developed gas infrastructure in the area.

The processed Kandra gas (40 MMSCFD) of 300 BTU will be commingled with 10 MMSCFD pipeline quality gas of 900-950 BTU/SCF heating value which will result in 50 MMSCFD of 430 BTU quality gas.

Introduction

  • Province:
  • Area:
  • Geological Setting:
  • Play Type:
  • Resource Potential:
  • Sindh
  • 314.43 km2
  • Khairpur-Jacobabad High
  • Structural
  • ~ 2.86TCF

Key Features

The block holds good potential for the development of a gas field at the level of Sui Main Limestone

Petroleum system is established in the area

Well-developed gas infrastructure within the block.

FIELD DEVELOPMENT

The field development envisages drilling and completing 12-14 additional wells, surface gathering lines and central processing facility for producing 120 MMSCFD of raw gas.
The low heating value Kandra gas (150 BTU/SCF) @ 40 MMSCFD after processing to 300 BTU will be used as fuel of 430 BTU for power generation after processing and comminling with 10 MMCFD pipeline quality gas.

POWER PROJECT

The processed Kandra gas (40 MMSCFD) of 300 BTU will be commingled with 10 MMSCFD pipeline quality gas of 900-950 BTU/SCF heating value which will result in 50 MMSCFD of 430 BTU quality gas.

This gas will be used as fuel for Combined Cycle Power Project of 120 megawatts electricity to be set up by Kandra Power Company.